KPLC LMCP Program

Client: Kenya Power and Lighting Company

Capacity: MV lines: ~70–75 km
LV lines: ~135–145 km
Connections: ~650–800
Network capacity: ~3–6 MW diversified load

Location: North Rift

Scope

  • Procurement of design, supply, installation, and commissioning
  • Extension of Medium Voltage (MV) lines
  • Construction of Low Voltage (LV) single phase lines
  • Supply and installation of service cables
  • Works focused on Last Mile electricity connectivity

Status: Ongoing (expected completion Q1 2026)

Impact: Over 4,000 rural residents to be served with clean, stable electricity.